Lesson 3: Create a calculator tape to calculate the development cost
In this lesson, you create a calculator tape to calculate the total cost to be invested on the development effort.
1 Click the dropdown list below the graphical grid area, and then select the Engineering stream.
2 Click the Calculator tab.
3 Click Tapes > New Tape.
4 Enter the name of the tape as Development cost.
5 Click Add Variable.
6 Specify the details for the new variable:
▪ In the Name field, enter DevelopmentCost.
▪ In the Description field, enter Total development cost for the project.
▪ In the Type field, select Formula.
▪ Enter the formula as BurdenedLabor*'Engineers'[PERIOD].
7 Click Tapes > Save Tape.
8 Click Save.
Lesson checkpoint
In this lesson, you learned to create a calculator tape to calculate the total development cost of the project.