Engine Status report
The Engine Status report takes each engine in turn and reports the percentage loading (that is, how busy it is, where fully loaded is 100%), how many interviews are currently running, and how many projects this covers. You can expand the projects count to see the project names if you want. If an engine is running interviews for projects that you cannot access, the report shows a single Other Projects entry for those projects.
To view the engine status report
1 In the Interviewing frame, click Engine Status.
2 To see the names of the names of the projects for which interviews are running, click the “plus” button to the left of the projects count. To return to the summary display, click the “minus” button.
Status icons
The report uses the following icons to indicate engines whose load is high or excessively high:
Icon
Description
This graphic is described in the surrounding text.
Information
The engine’s load is greater than 80%. The engine can still function normally with this load, but interviews might slow down.
This graphic is described in the surrounding text.
Warning
The engine’s current load is greater than 95%. This is excessively high and interviews will not run as quickly as they should.
If you regularly see this icon in reports, the UNICOM Intelligence administrator might be able to change the way in which interviews are allocated to session engines.
The load figures of 80% and 95% are the default values. Your UNICOM Intelligence administrator can tell you what the figures are for your site.
The report is a snapshot of activity at the point you request it. Refresh the report periodically to see up to date figures.