Architecting and designing : DoDAF : DoDAF 1.5 standard : Running DoDAF utilities : Generating OV-2 operational node connectivity diagrams from an existing operational node
  
Generating OV-2 operational node connectivity diagrams from an existing operational node
You can run the Operational Node to OV-2 Op Node Connectivity utility to generate OV-2 operational node connectivity diagrams from an existing operational node. When you run the utility, the appropriate operational nodes are located, placed on the diagram, and then connected with the appropriate needlines.
Prerequisite 
An OV-2 diagram must exist with the operational nodes and needlines.
Procedure
1 Click Tools > DoDAF Utilities.
2 Click Operational Node to OV-2.
All operational nodes in the current encyclopedia are presented.
3 Select one or more of these definitions from the list box, and then click Run.
4 Enter a name for each diagram to be created, and then click OK.
One or more OV-2 Operational Node Connectivity diagrams with Operational Node Symbols and their corresponding needlines.
See also
Running DoDAF utilities