Integrating : Focal Point and the Rational solution for Collaborative Lifecycle Management : Integrating with the Change and Configuration Management application : Restoring removed links to work items
  
Restoring removed links to work items
You can restore links that were removed from work items.
Before you begin
In a view that shows projects with linked elements, configure a view command for restoring removed links. For more information, see Adding view commands for bulk operations on artifacts in Rational solution for Collaborative Lifecycle Management applications
To restore links to work items, the links to restore must be removed.
Note If you changed the Rational solution for CLM server name, you can restore only the links to artifacts that were added after the server rename.
Procedure
1 Open the project view that has a view command for restoring links.
2 Select the element that links to the elements to restore links to.
3 Click the Restore the links that were last removed from the CLM server Restore link icon.
If the login page of the CCM application is displayed, log on by using your CCM application credentials.
4 On the “Select elements to restore links to” page, make these selections:
From the Attribute where the CLM servers were configured list, select the Integration Link attribute where the link to the CLM artifact is stored.
From the Allowed CLM servers list, select the CCM application to restore the links to.
Select the elements to restore links to by clicking the Add and Remove buttons. Click Next.
Results
The result is shown on the Bulk Publishing Result page. You can click the link of a work item to open it in the CCM application.
Go up to
Integrating with the Change and Configuration Management application